Serengeti Document Management Server Upgrade
Serengeti Document Management Server Upgrade
Home
Projects
Serengeti Document Management Server Upgrade
Project Brief
Impact
Impact
Priority and Funding
Project is priority 2 and is Compliance
Impact and Dependencies
Load Balancer work has to be done first in order to fix IE 11 issue
Outline
Serengeti Document Management Server Upgrade
Project Brief
Overview
Impact
Organisation
Completion Report
Build Test Document
Build Test Summary
Build Testing
Developer Testing
Development Technology Administrator Testing
Peer Testing
Integration Test Document
Integration Test Summary
Developer Testing
Functional Testing
Non-Functional Testing
Project Integration Testing
Deployment Checklist
Deployment
Training
Implementation Plan
Implementation Tasks
Rollout Steps
Business Requirements
Overview
Current Processes
Business Requirements
Proposed Business Processes
Data Requirements
User Acceptance Testing
Training
UAT: User Acceptance Test Plan
User Acceptance Test
‹ Overview
up
Organisation ›
This article was published on
Oct 24, 2016
Project Info
Project
Serengeti Document Management Server Upgrade
Code
COM031
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Susan Cooke
Current Stage
Close
Status
Closed
Start Date
19-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
23-Mar-2018
Overall Priority
Normal
Category
Compliance
More project information
Documentation
Initiate
No documents
Plan
Project Brief
Overview
Impact
Organisation
Execute
Build Test Document
Integration Test Document
Implementation Plan
Business Requirements
UAT: User Acceptance Test Plan
Deliver
Deployment Checklist
Close
Completion Report
Other
No documents