Rollout Academic Timetable Integration with Office 365 Calendar - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2017 BLUE 85.0 days 83.2 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Tuesday, 25 October 2016
Close Date
Wednesday, 16 August 2017
Project information
Project Code
COM032
Programme
ISG - Communication (COM)
Session
17/18
16/17
Organisational Unit
Application Development and Operations
Project Management Office (if relevant)
ISG PMO
Project Category
Discretionary
Overall Priority
Normal