Report for July 2017

Report Date
July 2017

Achievements in Last Period

  • No progress was made in this period - a new issue is documented below

Issues

  • PICCL Issue 8 - Work on MyEd upgrade is continuing and therefore the deployment of the updated portlet cannot be scheduled until advised of date of completion of upgrade of MyEd.

Next Steps

  • Deploy updated portlet
  • Close project

 

Target Datesort descending Title
31-Jul-2017 Closure
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
PICCL Issue 8 - Work on MyEd upgrade is continuing and therefore the deployment of the updated portlet cannot be scheduled until advised of date of completion of upgrade of MyEd.
Change Status
Activity
Approved budget
85.0 days
Activity this month
0.0 days
Activity this year
81.8 days
Activity to date
81.8 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.5 days

Project Info

Project
Rollout Academic Timetable Integration with Office 365 Calendar
Code
COM032
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Chris Copner
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
25-Oct-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Aug-2017
Overall Priority
Normal
Category
Discretionary