Rollout Steps

  • Personalised Email for Students (Options and Implementation)
    • Build Test Summary
    • Integration Test Summary
    • Build Testing
    • Closure Report
    • Developer Testing
    • Business Requirements
    • Developer Testing
    • Project Brief
      • Overview
      • Impact
      • Organisation
    • Development Technology Administrator Testing
    • Non-Functional Testing
    • Peer Testing
    • Project Integration Testing
    • User Acceptance Test (UAT) Plan
      • User Acceptance Test
      • Acceptance Tests and Outcomes
      • Blank page
      • Preliminary user/functional testing
    • Deployment Checklist
      • Deployment
      • Training
    • Implementation Plan
      • Implementation Tasks
      • Rollout Steps
    • Build Test Document
      • Build Test Summary
      • Build Testing
      • Developer Testing
      • Development Technology Administrator Testing
      • Peer Testing
    • Integration Test Document
      • Developer Testing
      • Functional Testing
      • Non-Functional Testing
    • Implementation Plan
      • Rollout Steps
  • ‹ Implementation Tasks
  • up
  • Build Test Document ›
This article was published on Oct 6, 2017

Project Info

Project
Personalised Email for Students (Options and Implementation)
Code
COM033
Programme
Digital Transformation - Integrated Identities (DTIP09)
Management Office
ISG PMO
Project Manager
Don MacIver
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
26-Oct-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
09-Feb-2018
Programme Priority
3
Overall Priority
Normal
Category
Discretionary
More project information

Documentation

Initiate
No documents
Plan
  • Project Brief
Execute
  • Build Test Summary
  • Integration Test Summary
  • Developer Testing
  • Business Requirements
  • Developer Testing
  • Development Technology Administrator Testing
  • Non-Functional Testing
  • Peer Testing
  • User Acceptance Test (UAT) Plan
  • Deployment Checklist
  • Implementation Plan
    • Implementation Tasks
    • Rollout Steps
  • Build Test Document
  • Integration Test Document
  • Implementation Plan
Deliver
No documents
Close
  • Closure Report
Other
  • Build Testing
  • Project Integration Testing

The University of Edinburgh

  • Terms & conditions
  • Privacy & cookies
  • Modern slavery
  • Website accessibility
  • Freedom of information publication scheme
University affiliations
MyEd login

The University of Edinburgh is a charitable body, registered in Scotland, with registration number SC005336, VAT Registration Number GB 592 9507 00, and is acknowledged by the UK authorities as a “Recognised body” which has been granted degree awarding powers.

Unless explicitly stated otherwise, all material is copyright © The University of Edinburgh 2022.

CMS login