Report for November 2017

Report Date
November 2017

 

Report for November 2017

Report Date
November 2017

Achievements in Last Period

  • Build review signed off 
  • Project moved to DTI Integrated Identities

Issues

  • None

Next Steps 

  • Acceptance review signed off
  • CAB request
  • Deployment meetings
  • Communications 
  • Deliver 12/12
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Budget moved to DTI Integrated Identities
Change Status
Activity
Approved budget
45.0 days
Activity this month
27.3 days
Activity this year
80.9 days
Activity to date
125.3 days
Estimate to complete current year
27.2 days
Estimate to complete future years
0.0 days