Report for December 2017
- Report Date
-
- December 2017
Achievements in Last Period
- Solution successfully deployed on 14th December 2017
- Issues
- None
Next Steps
- Resolve remaining JIRAs
- Complete closure report and circulate to project team key stakeholders for review
- Submit closure report to WIS
- Meeting to review new follow-on project on 22nd January 2018
- Approved budget
- 45.0 days
- Activity this month
- 27.3 days
- Activity this year
- 80.9 days
- Activity to date
- 125.3 days
- Estimate to complete current year
- 27.2 days
- Estimate to complete future years
- 0.0 days