Report for December 2017 *DRAFT*

Report Date
December 2017

 

Report for December 2017

Report Date
 
December 2017

Achievements in Last Period

  • Solution successfully deployed on 14th December 2017 
  • Issues
  • None

Next Steps 

  • Resolve remaining JIRAs 
  • Complete closure report and circulate to project team key stakeholders for review
  • Submit closure report to WIS 
  • Meeting to review new follow-on project on 22nd January 2018
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Budget moved to DTI Integrated Identities
Change Status
Activity
Approved budget
45.0 days
Activity this month
27.3 days
Activity this year
80.9 days
Activity to date
125.3 days
Estimate to complete current year
27.2 days
Estimate to complete future years
0.0 days