Report for January 2018

Report Date
January 2018
  • Achievements in Last Period

  • Solution successfully deployed on 14th December 2017 
  • Issues
    • None
  • Resolved remaining JIRAs 
  • Completed closure report and circulated to project team key stakeholders for review.
  • Closure signed-off
  • Meeting to review new follow-on project on 22nd January 2018
  • Next Steps 

  • Submit closure report to WIS 
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Project delivered, JIRA delivered and delivery reviewed. Closing project.
Change Status
Activity
Approved budget
45.0 days
Activity this month
1.0 day
Activity this year
104.6 days
Activity to date
149.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days