Report for August 2017

Report Date
August 2017

Achievements this Period

  • Decision made not to include Collaborative editing.
  • Closure agreed in principle once Collaborative Editing is removed from DEV. This requires a roll back.

Issues

  • Rollback of Collaborative Editing on DEV has not yet happened. This has held up the project closure.

 

Next Steps

  • Rollback DEV and document in JIRA what needs to be done to include Collaborative Editing.
  • Closure agreed
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
0.0 days
Activity this month
1.9 days
Activity this year
1.9 days
Activity to date
52.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Annual Wiki Upgrade
Code
COM034
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
10-Mar-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Sep-2017
Programme Priority
6
Overall Priority
Normal
Category
Compliance

Documentation