This project will upgrade the JIRA service to the latest stable release. This project is needed to avoid falling behind the release schedule for the JIRA service. Failure to upgrade this year can mean that future upgrades are more complex and costly.  The benefits are running an important service for projects on a supported version with potentially new features.  

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2017 BLUE 0.0 days 0.0 days 0.0

Project Info

Project
JIRA Upgrade 2017
Code
COM035
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Bill Lee
Current Stage
Close
Status
Closed
Start Date
06-Jun-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Aug-2017
Programme Priority
4
Overall Priority
Normal
Category
Compliance

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.