Current project status Report Date RAG Budget Effort Completed Effort to complete June 2018 BLUE 90.0 days 89.5 days 0.0 Content Status Closed Current Stage Close Start Date Monday, 4 September 2017 Close Date Friday, 22 June 2018 Project information Project Code COM037 Session 17/18 Organisational Unit IS Applications Project Management Office (if relevant) ISG PMO Project Category Compliance Funding Source Core Programme Priority 2 Overall Priority Normal