Report for April 2018

Report Date
April 2018

Achievements 

  • UAT carried out successfully.
  • Delivery re-planned, approved by stakeholders and assured by WIS. 
  • Deployment checklist and planning prepared. 

Issues

  • None.

 

Next Steps 

  • Cutover and delivery.  

The project is reporting GREEN.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
90.0 days
Activity this month
10.3 days
Activity this year
76.8 days
Activity to date
76.8 days
Estimate to complete current year
13.8 days
Estimate to complete future years
0.0 days

Project Info

Project
Update Grouper to v2.3.0
Code
COM037
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Susan Cooke
Current Stage
Close
Status
Closed
Start Date
04-Sep-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jun-2018
Programme Priority
2
Overall Priority
Normal
Category
Compliance