Report for April 2018
- Report Date
- April 2018
Achievements
- UAT carried out successfully.
- Delivery re-planned, approved by stakeholders and assured by WIS.
- Deployment checklist and planning prepared.
Issues
- None.
Next Steps
- Cutover and delivery.
The project is reporting GREEN.
- Approved budget
- 90.0 days
- Activity this month
- 10.3 days
- Activity this year
- 76.8 days
- Activity to date
- 76.8 days
- Estimate to complete current year
- 13.8 days
- Estimate to complete future years
- 0.0 days