Report for May 2018
- Report Date
- May 2018
Achievements
- Delivery of upgrade into Live
- Monitoring of live changes carried out successfully.
- Delivery sign-off approved by project team and reported to management
Issues
- None.
Next Steps
- Prepare closure report
- Approved budget
- 90.0 days
- Activity this month
- 10.2 days
- Activity this year
- 87.3 days
- Activity to date
- 87.3 days
- Estimate to complete current year
- 2.1 days
- Estimate to complete future years
- 0.0 days