Impact
Priority and Funding
It is proposed to set the priority at NORMAL. The project is a Core funded, compliance project.
Impact and Dependencies
We do not expect this project to impact on other developments currently underway. We will need our existing SOA experts to work on this project, however we will manage the resourcing so that other key projects such as Digital Transformation Notifications Roll-out, are not impacted.
The Core Systems initiative will progress with an integration strategy for university services. This will include external consultancy and will work closely with the COM038 project and its findings from the PoC.
Project Risks
Ref | Title | Impact | Probability | Risk | Status | Risk Owner | Date of Last Review | |
---|---|---|---|---|---|---|---|---|
1 | Risk to IDM Service due to technology end of life | Major | Low | GREEN | Open | Stefan Kaempf | 16-Nov-2017 | |
3 | Risk that development resource may not be available | Major | Medium | AMBER | Open | Bill Lee | 16-Nov-2017 | |
6 | Project Management Resource | Moderate | Low | GREEN | Open | Adam Wadee | 16-Nov-2017 | |
8 | Risk that PoC may not be possible | Moderate | Low | GREEN | Open | Bill Lee | 16-Nov-2017 |