Decommission legacy Windows hosting

This project will provide the resource to progress with that and have all content closed down or migrated to supported infrastructure.

  • Migrate windows hosted websites to an infrastructure that is supported.
  • Close down and decommission costly legacy physical servers
  • Identify and remove unused websites and databases

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2018 AMBER 50.0 days 28.0 days 22.0

Project Info

Project
Decommission legacy Windows hosting
Code
COM041
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Dawn Dodd
Current Stage
Integrate
Status
In Progress
Start Date
01-Nov-2017
Planning Date
19-Jan-2018
Delivery Date
23-Nov-2018
Close Date
07-Dec-2108
Programme Priority
6
Overall Priority
Normal
Category
Compliance