Organisation
Work/Task Breakdown
Project Management - 6 d
QA, Project sponsor & team meetings 7d
Planning 5d -
Analysis: 11d (inc Dev effort)
Migration: 20d
Closure : 1d
Project Governance
This project will follow the standard project governance in Project Services.
Any changes to major milestones (Initiation, Planning, Delivery, Closure) will be approved by the Project Sponsor, Project Team and WIS.
Major milestones achievements and changes will be submitted to WIS for approval/noting as necessary.
Project Stakeholders
Name | Business Area | Role |
---|---|---|
Alain Forrester | Service Management | Service Manager(Project Team Member) |
Ana Heyn | Production Management | Production Management |
Andrew Hobden | Production Management | Production Management |
Bill Lee | Development Services | Development Manager |
Business Web Service Owners | Various business areas | Senior Users(Project Team Members) |
Catherine Hetherington | Production Management | Joint Project Sponsor(Project Team Member) |
Dawn Dodd | Service Management | Joint Project Sponsor(Project Team Member) |
Glenda Gowden | Project Services | Business analyst(Project Team Member) |
Mark Lang | Development Technology | Development Technology Manager(Project Team Member) |
Megan Graham | Project Services | Project Manager(Project Team Member) |
Stefan Kaempf | Production Management | Production Manager |
Tim Gray | Programme Manager Project Services | Programme Manager |