Decommission legacy Windows hosting - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
May 2019 BLUE 50.0 days 72.5 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Wednesday, 1 November 2017
Planning Date
Friday, 19 January 2018
Delivery Date
Friday, 5 April 2019
Close Date
Friday, 17 May 2019
Project information
Project Code
COM041
Programme
ISG - Communication (COM)
Session
18/19
17/18
Organisational Unit
Application Development and Operations
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Compliance
Project Classification
Grow
Funding Source
Core
Programme Priority
6
Overall Priority
Normal