Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for July 2018 July 2018 AMBER GREEN GREEN AMBER
Report for June 2018 June 2018 GREEN GREEN GREEN GREEN
Report for May 2018 May 2018 GREEN GREEN GREEN GREEN
Report for April 2018 April 2018 GREEN GREEN GREEN GREEN
Report for March 2018 March 2018 GREEN GREEN GREEN GREEN
Report for February 2018 February 2018 GREEN GREEN GREEN GREEN
Report for January 2018 January 2018 GREEN GREEN GREEN GREEN
Report for December 2017 December 2017 GREEN GREEN GREEN GREEN
November 2017 Report November 2017 GREEN GREEN GREEN GREEN

Project Info

Project
Decommission legacy Windows hosting
Code
COM041
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Dawn Dodd
Current Stage
Integrate
Status
In Progress
Start Date
01-Nov-2017
Planning Date
19-Jan-2018
Delivery Date
23-Nov-2018
Close Date
07-Dec-2108
Programme Priority
6
Overall Priority
Normal
Category
Compliance