Report for September 2018

Report Date
September 2018

Achievements in Last Period

  • Work has continued on the site migration and checking

Issues

  • None

Next steps

  • Continue with site migrations and checking.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days