Report for September 2018

Report Date
October 2018

Achievements in Last Period

  • Work has continued on the site migration and checking
  • Two additional colleagues in Service Management now assisting with migrations

Issues

  • An issue with licensing on the replacement server held up progress, this has now been resolved.¬†

Next steps

  • Continue with site migrations and checking.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
2.2 days
Activity this year
6.4 days
Activity to date
34.1 days
Estimate to complete current year
1.5 days
Estimate to complete future years
0.0 days