Report for December 2018

Report Date
December 2018

Achievements in Last Period

  • Work has continued on the site migration and checking

Issues

  • It is likely that some work will not be completed¬†before the next milestone. A meeting is scheduled with Production in the next reporting period to discuss how to handle any outstanding work.

Next steps

  • Complete¬†site migrations and checking.
  • Move to closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
0.0 days
Activity this year
18.0 days
Activity to date
46.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days