Report for January 2019

Report Date
January 2019

Achievements in Last Period

  • Work has continued on the site migration and checking
  • Agreement reached with the project team and key stakeholders to move out migration completion and closure milestones
  • The project will report as GREEN although the milestones have moved out 6 weeks

Issues

  • No new issues

Next steps

  • Complete site migrations and checking.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
1.7 days
Activity this year
28.0 days
Activity to date
56.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days