Report for April 2018

Report Date
April 2019

Achievements in Last Period

  • Site migrations completed and signed off

Issues

  • Project closure milestone moved out due to lack of Project Manager availability 

Next steps

  • Complete project closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
AMBER: The closure milestone has been moved out due to the project manager's availability.
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
1.0 day
Activity this year
44.0 days
Activity to date
72.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days