Report for December 2017

Report Date
December 2017

 

Achievements This Period

  • Project Planning almost complete.
  • Project Brief completed.

Issues

  • Project Planning milestone approved at WIS, to be moved to 19th January 2018, due to new PM workload and availability of key stakeholders during the holiday period.

Next Steps

  • Completion of Project Brief, to include estimates and milestone dates based on resources.
  • Planning completion milestone will be achieved and approved at WIS.

Milestones

  Target Date            Title
  19-Jan-2018   End of Planning
  23-Feb-2018   Business Analysis complete       
  30-Mar-2018   Design sign-off
  27-Apr-2018   Build complete PPBR
  17-May-2018   Integration Sign-off
  15-Jun-2018   Acceptance sign-off
  29-Jun-2018   Delivery sign-off
  13-Jul-2018   Closure complete
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
RAG status is GREEN.
Change Status
Activity
Approved budget
50.0 days
Activity this month
2.0 days
Activity this year
6.0 days
Activity to date
6.0 days
Estimate to complete current year
44.0 days
Estimate to complete future years
0.0 days