Report for January 2018

Report Date
January 2018

 

Report for January 2018

Report Date
January 2018

 

Achievements This Period

  • Project Planning Milestone complete.
  • Project Analysis in Progress and on track

Issues

  • Recruitment exercise has been unsuccessful and has led to an extension of the time period, in the hope that a suitable candidate will be found.  Contingency will be for Project services to continue with some of the design work, with the assistance of the Service management team.

Next Steps

  • Completion of Project Analysis milestone.
  • Project Design milestone commencement.
  • Recruitment extension and interview of Student intern resource.

Milestones

Target Datesort descending Title
19-Jan-2018 End of Planning
23-Feb-2018 Business Analysis complete
30-Mar-2018 Design sign-off
02-Jul-2018 Migration complete
13-Jul-2018 Closure complete
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Project analysis is going well. Initial analysis has found that there may be around 40% of services not required for migration to the new infrastructure.
Change Status
Activity
Approved budget
50.0 days
Activity this month
6.9 days
Activity this year
13.9 days
Activity to date
13.9 days
Estimate to complete current year
35.5 days
Estimate to complete future years
0.0 days