Report for February 2018

Report Date
February 2018

Report for February 2018 Megan Graham

 

Achievements This Period

  • Completion of Project Analysis milestone.
  • Project Design milestone completed 6 weeks ahead of schedule.
  • Web migrations have commenced to the new infrastructure.
  • Wiki has been updated with the process and plan for migrations.
  • Recruitment extension and interview of Student intern resource.

Issues

  • Recruitment exercise has been unsuccessful and has led to an extension of the time period, in the hope that a suitable candidate will be found.  Contingency is for the Project services resource to extend their work to perform the less complex migrations, with support and training from Service Management.

Next Steps

  • Make headway towards completing the migrations to the new infrastructure.
  • New Posting for recruitment has been sent out, due to lack of success of the previous posting.

Milestones

Target Datesort descending Title
02-Jul-2018 Migration complete
13-Jul-2018 Closure complete
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
RAG status of GREEN as project ahead of schedule and on track.
Change Status
Activity
Approved budget
50.0 days
Activity this month
5.6 days
Activity this year
16.8 days
Activity to date
16.8 days
Estimate to complete current year
33.2 days
Estimate to complete future years
0.0 days