Report for March 2018

Report Date
March 2018

Achievements This Period

  • Web migrations are continuing to the new infrastructure. Many of them are complicated and time consuming, requiring additional time from Service manager to support the technical resources, but we are still within the project tolerance for timescales.
  • Wiki has been updated with the process and plan for migrations.
  • Recruitment extension and interview of Student intern resource.

Issues

  • Recruitment exercise has been unsuccessful and has led to an extension of the time period, in the hope that a suitable candidate will be found.  Contingency is for the Project services resource to extend their work to perform the less complex migrations, with support and training from Service Management.

Next Steps

  • Make headway towards completing the migrations to the new infrastructure.

Milestones

 Target Datesort descending  Title
 02-Jul-2018  Migration complete
 13-Jul-2018  Closure complete
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
5.0 days
Activity this year
23.0 days
Activity to date
23.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
27.0 days