Report for May 2018

Report Date
May 2018

Achievements This Period

  • Web migrations are continuing to the new infrastructure. Many of them are complicated and time consuming, requiring additional time from Service manager to support the technical resources, but we are still within the project tolerance for timescales.
  • Wiki has been updated with the process and plan for migrations.

Issues

  • Recruitment exercise has been unsuccessful whereby a decision for the work to be completed by service management and PMO has been made.  Project services resource to extend their work to perform the less complex migrations, communications and wiki updates with support and training from Service Management.

Next Steps

  • Make headway towards completing the migrations to the new infrastructure.

Milestones

 Target Datesort descending  Title
 02-Jul-2018  Migration complete
 13-Jul-2018  Closure complete
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
2.0 days
Activity this year
26.0 days
Activity to date
26.0 days
Estimate to complete current year
24.0 days
Estimate to complete future years
0.0 days