Report for July 2018

Report Date
July 2018

Achievements in Last Period

  • Good progress made on easier sites.
  • Committee Intranet site majority are already migrated, these need to be cross-checked.

Issues

  • Due to the time taken so far to migrate sites, annual leave and the change control period, this project will now move into November --> December closure

Next steps

  • Continue with site migrations and checking.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
CHANGE - Milestones have been revised this month; therefore, status is AMBER.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
1.0 day
Activity this year
28.0 days
Activity to date
28.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
22.0 days

Project Info

Project
Decommission legacy Windows hosting
Code
COM041
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Dawn Dodd
Current Stage
Integrate
Status
In Progress
Start Date
01-Nov-2017
Planning Date
19-Jan-2018
Delivery Date
23-Nov-2018
Close Date
07-Dec-2108
Programme Priority
6
Overall Priority
Normal
Category
Compliance