Report for July 2018

Report Date
July 2018

Achievements in Last Period

  • Good progress made on easier sites.
  • Committee Intranet site majority are already migrated, these need to be cross-checked.

Issues

  • Due to the time taken so far to migrate sites, annual leave and the change control period, this project will now move into November --> December closure

Next steps

  • Continue with site migrations and checking.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
CHANGE - Milestones have been revised this month; therefore, status is AMBER.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
1.0 day
Activity this year
28.0 days
Activity to date
28.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
22.0 days