Closure Report

Project Summary

COM044 delivered ahead of schedule, whilst coping with some production delays

COM044 was a very successful smooth running project due to the project team working well together

COM044 decommissioned the old Serengeti databases before closure

Scope

The priorities were as follows:

The requirements were the migration / upgrade of the Serengeti databases to new 12c Oracle databases on the existing Oracle 12c servers.

Objectives & Deliverables

Objective 2 was completed in Test Rail, but full information of what was delivered is covered in Deliverable 4

In addition COM044 provided the decommissioning in Objective (O3) and Deliverables (D5-7) as well in this project

 

Deliverables

MoSCoW

Achieved    
O1

To provide migrated/upgraded databases

 

 
D1

Migrated and upgraded databases to Oracle 12C Dev

 Must have

    Y
D2 Migrated and upgraded databases to Oracle 12C Test  Must have     Y
D3 Migrated and upgraded databases to Oracle 12C Live  Must have     Y
O2 To provide repeatable test scripts in Test Rail    
D4

Run existing / create Test Rail scripts to verify that the Serengeti Applications works as expected

[What was provided was that the existing business Test scripts  were used to verify that the Serengeti Applications worked as expected]

 Could have

 

[Completed]

 

    N

  

   [Y]

 

O3 To decommission the old databases    
D5 Decommissioned databases in Oracle 11G Dev [Completed]     [Y]
D6 Decommissioned databases in Oracle 11G Test [Completed]     [Y]
D7 Decommissioned databases in Oracle 11G Live [Completed]     [Y]

Benefits

Item

Benefits Achieved
  •  
Ongoing security updated and support on newer server infrastructure Y - security updates were carried out by production separately from COM044, but planned and worked along side with COM044 replanning to suit the supplier's dates
  •  
Documentation updated for future software development processes Y - TAD has been updated
  •  
The old databases in Dev, Test and Live were decommissioned, which clears up old data Y - completed 3-Apr

Success Criteria

Item Success Criteria Achieved
  •  
Serengeti databases on Dev, Test and Live have been successfully migrated and upgraded to Oracle 12 (Must Have)   Y
  •  
The software maintains its current working condition and causes minimal disruption during the upgrade   Y
  •  
That the Serengeti application works as expected   Y
  •  
Serengeti databases on Dev, Test and Live have been successfully decommissioned in Oracle 11  

Analysis of Resource Usage:

Staff Usage Estimate: 61 days

  • Proposal:  50 days
  • Brief:  61 days
  • Approved:  46 days

Staff Usage Actual: 40.5 days

Other Resource Estimate: £xxx

Other Resource Actual: £xxx

Other Resource Variance: xx%

Outcome

Explanation for variance

Production had to complete Serengeti application security patching in Live (that had previously been completed in Test and Live before COM044 started )

  • this was arranged for 13-Feb and this took the supplier until 14-Feb to complete
  • after it was completed it was realised that Live had been upgraded to a more recent security patch than what had been applied to  Dev and Test
  • the supplier then arranged to patch Weblogic in Dev and Test on 28-Feb (both were 1/2 hour patches).  Further information can be found in
  • This production work delayed the COM044 plan, however while this delay was occurring  -
    • Dev Tech pro-actively suggested that there was one piece of work that could be completed in Live in the meantime, in preparation for the Go Live work
    • This resulted in some slight replanning so that the project could continue on schedule
  • The project successfully completed with a lower budget, due to the smooth running of the project and a good project team

Key Learning Points

Production Support and  COM044 project team worked well alongside each other to ensure the Security patches  were taken into account in the COM044 plan

Excellent Dev Tech WIKI implementation plan. Apps Support requested a link to, so that it could be maintained in the Apps Support WIKI.

Outstanding Issues

  • No outstanding issues

Project Info

Project
Serengeti Database Annual Migration / Upgrade
Code
COM044
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Susan Cooke
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Nov-2018
Planning Date
18-Jan-2019
Delivery Date
20-Mar-2019
Close Date
11-Apr-2019
Overall Priority
Normal
Category
Compliance