Serengeti Database Annual Migration / Upgrade - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2019 BLUE 46.0 days 41.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Friday, 2 November 2018
Planning Date
Friday, 18 January 2019
Delivery Date
Wednesday, 20 March 2019
Close Date
Thursday, 11 April 2019
Project information
Project Code
COM044
Session
18/19
Organisational Unit
IS Applications
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Compliance
Project Classification
Run
Funding Source
Core
Overall Priority
Normal