Monthly Project Report
- Report Date
- February 2019
Achievements
- Repointed Serengeti, EFIN and Estates applications on Dev
- Apps support completed testing in Dev of the updated Serengeti database
- Dev testing complete
- Was a delay during February due to Serengeti security patching being out of sync, however this has been resolved and as of 1-Mar the Security patching is in line in Dev, Test and Live with the October 18 release
- This now enabled the project to continue with building the TEST Database
- Built Test database
- Built Live database
- Start upgrading the Test database
Issues
-
No issues
Next Steps
- Finish upgrading Test database
- Apps support complete testing in TEST of the updated Serengeti database
- Repoint Serengeti, EFIN and Estates applications on TEST
- Complete Integration Milestone
- Complete TEST testing
- Sign off UAT of Serengeti database
- Upgrade LIVE database
- Repoint Serengeti, EFIN and Estates applications on LIVE
- Business check out upgraded database in Live
- Deliver Serengeti database upgrade in Live
GREEN RAG status
Milestones
Execute | Integration | 04-Mar-2019 |
Execute | Acceptance | 21-Mar-2019 |
Deliver | Deliver | 28-Mar-2019 |
Deliver | Deployment Sign Off Review | 29-Apr-2019 |
Close | Closure | 30-Apr-2019 |
- Approved budget
- 61.0 days
- Activity this month
- 11.0 days
- Activity this year
- 27.0 days
- Activity to date
- 27.0 days
- Estimate to complete current year
- 38.0 days
- Estimate to complete future years
- 0.0 days