Monthly Project Report
- Report Date
- March 2019
Achievements
- Finished upgrading Test database
- Apps support completed testing in TEST of the updated Serengeti database
- Repointed Serengeti, EFIN and Estates applications on TEST
- Completed Integration Milestone
- Completed TEST testing
- Signed off UAT of Serengeti database
- Upgraded LIVE database
- Repointed Serengeti, EFIN and Estates applications on LIVE
- Business checked out upgraded database in Live
- Delivered Serengeti database upgrade in Live 19 to 20 Mar
- Revised budget and milestones approved
Issues
-
No issues
Next Steps
- Deployment Check list
- Deployment Sign off Review
- Decommission old Serengeti Databases in Dev, Test and Live
- COM044 Closure report
- Close project COM044
GREEN RAG status
Milestones
Deliver | Deployment Sign Off Review | 10-Apr-2019 |
Close | Closure | 11-Apr-2019 |
- Approved budget
- 46.0 days
- Activity this month
- 9.0 days
- Activity this year
- 37.0 days
- Activity to date
- 37.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days