Monthly Project Report

Report Date
March 2019

Achievements

  • Finished upgrading Test database
  • Apps support completed testing in TEST of the updated Serengeti database
  • Repointed Serengeti, EFIN and Estates applications on TEST
  • Completed Integration Milestone
  • Completed TEST testing
  • Signed off UAT of Serengeti database
  • Upgraded LIVE database
  • Repointed Serengeti, EFIN and Estates applications on LIVE
  • Business checked out upgraded database in Live
  • Delivered Serengeti database upgrade in Live 19 to 20 Mar
  • Revised budget and milestones approved

Issues

  • No issues

Next Steps

  • Deployment Check list
  • Deployment Sign off Review
  • Decommission old Serengeti Databases in Dev, Test and Live
  • COM044 Closure report
  • Close project COM044

 

GREEN RAG status

Milestones

Deliver Deployment Sign Off Review 10-Apr-2019
Close Closure 11-Apr-2019
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
46.0 days
Activity this month
9.0 days
Activity this year
37.0 days
Activity to date
37.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Serengeti Database Annual Migration / Upgrade
Code
COM044
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Susan Cooke
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Nov-2018
Planning Date
18-Jan-2019
Delivery Date
20-Mar-2019
Close Date
11-Apr-2019
Overall Priority
Normal
Category
Compliance