This project will deliver an upgrade to the IDM database. The database is currently on physical Oracle 11g infrastructure, and Oracle will withdraw extended support for 11g at the end of 2020.

This project will look to move this onto the physical Oracle 12c infrastructure with an analysis to take place to ascertain if it possible to move to the new virtual machines on the metro stretched cluster

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2021 AMBER 169.0 days 154.0 days 15.0

Project Info

Project
IDM Database Upgrade
Code
COM045
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Susan Cooke
Current Stage
Build
Status
In Progress
Project Classification
Run
Start Date
10-Dec-2018
Planning Date
01-Feb-2019
Delivery Date
04-Oct-2021
Close Date
29-Oct-2021
Overall Priority
Normal
Category
Compliance