Organisation

Work/Task Breakdown

stage task Team Estimated effort
Initiation  Prepare initiation documentation & project website Project Services 0.5d
Planning Project planning & discussions PM (2d) + Project Team (1d) 3d
  Programme Management & mentoring Project Services 2d
  Team meetings Project Team 2d
  Project Sponsor   1d

Analysis & Design

R&D – Configuration  Service Management 1d
  Options re Puppetizing of JIRA  Development Technology 1d
  Update TAD - check Apache/Tomcat versions Development Technology 0.5d
  Determine access restrictions Development Technology 2d

 Build

Refresh DEV and TEST from LIVE

Development Technology (2x1)

2d
  Upgrade JIRA in DEV Development Technology 2d
  Peer testing 

Development Services (0.5)

Service Management (0.5)

1d
  Upgrade JIRA in TEST   Development Technology 2d
Acceptance User Acceptance Testing  

Development Services (1)

Ser vice Management (3)

4d
  Rework Development Technology 1d
  Implementation Plan Development Technology 0.5d
  Peer Review  Development Services 1d
  Deployment checklist Applications Management 0.5d
Deployment Deployment into LIVE Development Technology 1d
  Deployment review Project Team 0.5d
Closure Completion Report Project Services 1d
  Closure review Project Team 0.5d
    TOTAL 30d

 

Resources, Skills and Costs

The project is funded through the ISG, Communications Programme.

Staff Resource Estimate Current Year - 30 days

 

Project Governance

The governance used for this project will be the standard project governance and procedures from WIS.

Project Stakeholders

Name Business Area Role
Alain Forrester Service Management Service Operations Manager (Project Team)
Ana Heyn Production Management Production Manager
Bill Lee IS Applications Development Services Project Sponsor (Project Team)
David Watters ISG Project Services Programme Manager (Project Team)
Hugh Brown ISG Production Management Production Rep (Project Team)
Nik Pardoe Development Technology Technical Lead (Project Team)
Yiwei Jing ISG Project Services Project Manager (Project Team)

 

Project Estimations

See above

 

Project Info

Project
Annual JIRA Upgrade
Code
COM047
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Bill Lee
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Jun-2019
Planning Date
18-Jul-2019
Delivery Date
27-Aug-2019
Close Date
20-Sep-2019
Overall Priority
Normal
Category
Compliance