Report for July 2019
- Report Date
- July 2019
Achievements
- Project brief signed off
- Familiarisation & analysis work undertaken by project team
- Preparations made for upgrade in DEV
Issues
- None
Next steps
- Refresh data from LIVE
- Upgrade in DEV
- Apply upgrade to TEST
Milestones
Stage | Milestone | Due Date |
---|---|---|
Build | Build review | 06-Aug-2019 |
Accept | Acceptance Review | 22-Aug-2019 |
Deliver | Deployment to LIVE | 27-Aug-2019 |
Deliver | Deployment Review | 06-Sep-2019 |
Close | Project closure | 20-Sep-2019 |
- Approved budget
- 16.0 days
- Activity this month
- 9.5 days
- Activity this year
- 11.0 days
- Activity to date
- 11.0 days
- Estimate to complete current year
- 0.1 days
- Estimate to complete future years
- 19.0 days