Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for July 2021 July 2021 BLUE BLUE BLUE BLUE
Report for June 2021 June 2021 GREEN GREEN GREEN GREEN
Report for May 2021 May 2021 GREEN GREEN GREEN GREEN
Report for April 2021 April 2021 AMBER AMBER GREEN AMBER Within Tolerance
Report for March 2021 March 2021 AMBER AMBER GREEN AMBER Within Tolerance
Report for February 2021 February 2021 AMBER GREEN GREEN AMBER Within Tolerance
Report for January 2021 January 2021 AMBER GREEN GREEN AMBER No Change
Report for December 2020 December 2020 AMBER GREEN GREEN AMBER No Change
Report for November 20 November 2020 AMBER GREEN GREEN AMBER No Change
Report for October 20 October 2020 GREEN GREEN GREEN GREEN No Change
Report for September 2020 September 2020 AMBER GREEN GREEN AMBER Significant
Report for August 2020 August 2020 AMBER AMBER AMBER AMBER Significant
Report for July 2020 July 2020 AMBER AMBER GREEN AMBER Significant
Report for June 2020 June 2020 GREEN AMBER GREEN GREEN Moderate
Report for May 2020 May 2020 GREEN AMBER GREEN AMBER Within Tolerance
Report for April 2020 April 2020 AMBER AMBER AMBER AMBER Significant
Report for March 2020 March 2020 AMBER GREEN AMBER AMBER Moderate
Report for February 2020 February 2020 AMBER GREEN GREEN AMBER No Change
Report for January 2020 January 2020 GREEN GREEN GREEN GREEN No Change
Report for December 2019 December 2019 GREEN GREEN GREEN AMBER No Change
Report for November 2019 November 2019 GREEN GREEN GREEN RED No Change
Report for October 2019 October 2019 GREEN GREEN GREEN GREEN No Change

Project Info

Project
Office 365 Security Hardening
Code
COM051
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
09-Sep-2019
Planning Date
25-Oct-2019
Delivery Date
14-Jul-2021
Close Date
23-Jul-2021
Overall Priority
Higher
Category
Compliance

Documentation