Report for August 2020

Report Date
August 2020

Achievements in Last Period:

New exclusion groups have been created to support a change in Microsoft policy for auto-forwarding. 

Issues:

  • The project continues to run without approved budget. 
  • The implementation of the Warning Banner solution is subject to ITC approval. Concerns from the pilot have been escalated to this forum for consideration 
  • A change in Microsoft policy has recently been announced which means that the original ITI elements of the auto-forwarding work is now deemed redundant.

Next Steps:

  • The ITC is due to meet on the 16th September. 
  • Once clearer direction is given, the project plan will be revised to reflect decisions taken for the deployment of the Warning Banner and Auto-forwarding solutions.
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
RAG Commentary
Future direction of the project is subject to ITC guidance. A meeting is scheduled for Mid-September, the outcome from which is likely to affect: time, cost and scope.
Change Status
Time
Within Tolerance
Cost
Significant
Scope
Within Tolerance
Overall
Significant
Has formal escalation taken place?
No
Change Commentary
An increase in project budget has yet to be agreed.
Activity
Approved budget
50.0 days
Activity this month
7.0 days
Activity this year
7.0 days
Activity to date
80.0 days
Estimate to complete current year
15.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Office 365 Security Hardening
Code
COM051
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
09-Sep-2019
Planning Date
25-Oct-2019
Delivery Date
14-Jul-2021
Close Date
23-Jul-2021
Overall Priority
Higher
Category
Compliance

Documentation