Report for February 2021
- Report Date
- February 2021
Achievements in Last Period
- Project team met to agree final steps and actions required for outstanding communications
- Sponsor approved comms plan and comms text for auto-forwarding
- Agreed date for auto-forwarding comms to go out
Issues
- Remaining milestones moved out, with closure now planned for early April
Next Steps
- Warning banner changes to be made
- Final comms to be drafted and issued
- Auto-forwarding to be enabled
- Final steps to be signed off
- Project Closure
Milestones
D2.1 Block Rules to prevent Auto-Forwarding |
02-Apr-2021 |
Project Closure |
09-Apr-2021 |
RAG Commentary
Project is AMBER
This is because of the remaining milestones being adjusted this month. We now have agreement on the individual tasks to be completed and dates for these.
- Approved budget
- 110.0 days
- Activity this month
- 3.3 days
- Activity this year
- 34.8 days
- Activity to date
- 107.7 days
- Estimate to complete current year
- 1.5 days
- Estimate to complete future years
- 0.0 days