Report for May 2021
- Report Date
- May 2021
Achievements in Last Period
- Meeting held 26 April 21 to address queries raised by John and Steve
- Membership lists have been reviewed and the groups have now been updated. Due to leave this will be shared with the group on return
- Service Management have set up a functional account for comms
- Service Management have set up a SharePoint site for the email service
Issues
- As we had not anticipated a change to the groups for autoforwarding this has meant some further work for ITI but delayed due to leave
Next Steps
- Alex to confirm how to set up the forwarding group
- Deploy to Live date agreed (unconfirmed at third week in June)
- Comms sent out for deployment to Live
- Deploy autoforwarding to Live
Milestones
14-Jun-2021 |
|
21-Jun-2021 |
- Approved budget
- 110.0 days
- Activity this month
- 1.0 day
- Activity this year
- 41.0 days
- Activity to date
- 114.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days