Report for July 2021
- Report Date
- July 2021
Achievements in Last Period
- Project closed 30/7/21
- Autoforwarding has been taken into service to complete - see autoforwarding milestone and closure report for timeline
- Approved budget
- 118.0 days
- Activity this month
- 4.0 days
- Activity this year
- 46.0 days
- Activity to date
- 119.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days