Report for April 2020

Report Date
April 2020

 

Achievements in Last Period:

  • The deployment of Global Admin Account restrictions is in progress and due for completion.
  • The email warning banner for ISG was scheduled for deployment at the end of April.
  • Initial testing of the auto forwarding ban has been completed

Issues:

  • CPAG members have yet to confirm whether they wish to opt-in/opt-out of the email warning banner work.
  • There is no communication strategy in place for the roll-out of the auto forwarding ban.

Next Steps:

  • A further re-plan is required to include a communication and roll-out of the auto forwarding ban.
  • Agreement is to be reached on who is best placed to manage the communication and timelines to achieve.

 

Milestones:

Tightening Access Controls 01-May-2020
Deploy Block Rules for Auto-Forwarding       01-May-2020
Warning banner on external emails 15-May-2020
DSOR 22-May-2020
Project Closure 29-May-2020
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
RAG Commentary
The Head of Service Management was previously going to oversee the communication strategy for the security hardening changes. In his absence and with his work now being distributed across other Service Managers, the ability to take the work forward quickly is now a new challenge. A re-plan with extended time-lines to absorb the increase in scope amongst existing team members is presently under consideration.
Change Status
Time
No Change
Cost
No Change
Scope
Significant
Overall
Significant
Has formal escalation taken place?
Yes
Escalated to
The replacement Project Sponsor is aware of the present dilemma.
Change Commentary
From information shared as part of a Handover from the Head of Service Management, the additional work in progressing with a communications piece is likely to be significant.
Activity
Approved budget
50.0 days
Activity this month
8.0 days
Activity this year
31.5 days
Activity to date
31.5 days
Estimate to complete current year
18.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Office 365 Security Hardening
Code
COM051
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
09-Sep-2019
Planning Date
25-Oct-2019
Delivery Date
14-Jul-2021
Close Date
23-Jul-2021
Overall Priority
Higher
Category
Compliance