Report for April 2020
- Report Date
- April 2020
Achievements in Last Period:
- The deployment of Global Admin Account restrictions is in progress and due for completion.
- The email warning banner for ISG was scheduled for deployment at the end of April.
- Initial testing of the auto forwarding ban has been completed
Issues:
- CPAG members have yet to confirm whether they wish to opt-in/opt-out of the email warning banner work.
- There is no communication strategy in place for the roll-out of the auto forwarding ban.
Next Steps:
- A further re-plan is required to include a communication and roll-out of the auto forwarding ban.
- Agreement is to be reached on who is best placed to manage the communication and timelines to achieve.
Milestones:
Tightening Access Controls | 01-May-2020 |
Deploy Block Rules for Auto-Forwarding | 01-May-2020 |
Warning banner on external emails | 15-May-2020 |
DSOR | 22-May-2020 |
Project Closure | 29-May-2020 |
- Approved budget
- 50.0 days
- Activity this month
- 8.0 days
- Activity this year
- 31.5 days
- Activity to date
- 31.5 days
- Estimate to complete current year
- 18.5 days
- Estimate to complete future years
- 0.0 days