Report for February 2021

Report Date
February 2021

Achievements this period

  • Purchase of Crowd Server confirmed
  • Project Brief sign off achieved
  • Planning meeting to re-plan the milestones around Dev Tech availability completed, with a start at the beginning of March

Issues

  • None

Next Steps

  • Setup Crowd Server on DEV

Milestones

Build sign off 12-Mar-2021
Integration sign off 09-Apr-2021
Acceptance sign off 23-Apr-2021
Research complete into SaaS Solution 30-Apr-2021
Deployment 05-May-2021
Deployment Sign off Review 19-May-2021
Decommission complete 28-May-2021
Closure 04-Jun-2021
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
100.0 days
Activity this month
4.0 days
Activity this year
15.0 days
Activity to date
15.0 days
Estimate to complete current year
80.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Wiki Crowd Implementation
Code
COM057
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dawn Dodd
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
02-Oct-2020
Planning Date
20-Nov-2020
Delivery Date
27-Jul-2021
Close Date
09-Sep-2021
Programme Priority
2
Overall Priority
Normal
Category
Compliance