Report for February 2021
- Report Date
- February 2021
Achievements this period
- Purchase of Crowd Server confirmed
- Project Brief sign off achieved
- Planning meeting to re-plan the milestones around Dev Tech availability completed, with a start at the beginning of March
Issues
- None
Next Steps
- Setup Crowd Server on DEV
Milestones
Build sign off | 12-Mar-2021 |
Integration sign off | 09-Apr-2021 |
Acceptance sign off | 23-Apr-2021 |
Research complete into SaaS Solution | 30-Apr-2021 |
Deployment | 05-May-2021 |
Deployment Sign off Review | 19-May-2021 |
Decommission complete | 28-May-2021 |
Closure | 04-Jun-2021 |
- Approved budget
- 100.0 days
- Activity this month
- 4.0 days
- Activity this year
- 15.0 days
- Activity to date
- 15.0 days
- Estimate to complete current year
- 80.0 days
- Estimate to complete future years
- 0.0 days