Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for May 2021 May 2021 GREEN GREEN GREEN GREEN
Report for April 2021 April 2021 AMBER AMBER GREEN AMBER
Report for March 2021 March 2021 AMBER AMBER GREEN AMBER
Report for February 2021 February 2021 GREEN AMBER AMBER AMBER
Report for January 2021 January 2021 AMBER AMBER GREEN AMBER
Report for October 2020 October 2020 AMBER

Project Info

Project
VRS Rewrite
Code
COM059
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Alex Carter
Current Stage
Execute
Status
In Progress
Project Classification
Grow
Start Date
04-Dec-2020
Planning Date
28-Jan-2021
Delivery Date
13-Jan-2022
Close Date
25-Feb-2022
Programme Priority
1
Overall Priority
Normal
Category
Compliance

Documentation