Report for October 2020

Report Date
October 2020

Project flagged as AMBER due to delayed start. Further details in COM PRICCL Item 64. The project will now start in late November 2020.

Project Status
RAG Status
Overall
AMBER
RAG Commentary
The project was due to start in late October, however due to a conflict on PM and business partner time, the start date will be delayed to late November. At this stage, the delivery date is not impacted.
Change Status
Time
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
VRS Rewrite
Code
COM059
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Alex Carter
Current Stage
Execute
Status
In Progress
Project Classification
Grow
Start Date
04-Dec-2020
Planning Date
28-Jan-2021
Delivery Date
13-Jan-2022
Close Date
25-Feb-2022
Programme Priority
1
Overall Priority
Normal
Category
Compliance