Report for January 2021

Report Date
January 2021

Achievements this period

  • Project brief drafted and feedback received
  • Project approach agreed with key stakeholders
  • Draft communications plan and stakeholder maps created
  • Development resources secured

Issues

  • There has beed a slight delay (one week) to complete planning. 
  • The project estimation at the end of planning is 610 days, the available budget is only 200 days. This has not been resolved yet. 

Next Steps

  • Complete planning review
  • Finalise communications plan and stakeholder maps
  • Start business analysis
  • Start system design 
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
AMBER: The project is AMBER as the estimation during planning far outweighs the available budget.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
200.0 days
Activity this month
16.0 days
Activity this year
16.0 days
Activity to date
16.0 days
Estimate to complete current year
177.0 days
Estimate to complete future years
0.0 days

Project Info

Project
VRS Rewrite
Code
COM059
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Alex Carter
Current Stage
Execute
Status
In Progress
Project Classification
Grow
Start Date
04-Dec-2020
Planning Date
28-Jan-2021
Delivery Date
13-Jan-2022
Close Date
25-Feb-2022
Programme Priority
1
Overall Priority
Normal
Category
Compliance

Documentation