Report for May 2021

Report Date
May 2021

Achievements this period

  • Work on developing the IDM functional areas has continued.
  • Two design documents for the VRS component were written and circulated for review.
  • At the review meeting on 31.05.2021, agreement was reached to progress with the development of the VRS components with SharePoint. 
  • After many delays, some progress has been made on the infrastructure, we expect to have a DEV environment in place during the next reporting period. 
  • Stakeholder workshops were held, the results feeding into the future shape of the service.

Issues

  • Pressure on the project manager's availability have resulted in the PM being handed over to Colin Watt. A handover is in place, this will be completed by 03.06.2021.

Next Steps

  • Start work on the SharePoint build
  • Continue building the IDM components including an intern build review
  • Complete DEV environment
  • Continue with stakeholder engagement, a user group meeting is scheduled for 24.06.2021.

RAG Commentary

  • The project returns to GREEN this month.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
AMBER: The project is AMBER due to the continued delay on the design decision on the VRS components.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
610.0 days
Activity this month
41.0 days
Activity this year
95.0 days
Activity to date
95.0 days
Estimate to complete current year
193.0 days
Estimate to complete future years
326.0 days

Project Info

Project
VRS Rewrite
Code
COM059
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Alex Carter
Current Stage
Execute
Status
In Progress
Project Classification
Grow
Start Date
04-Dec-2020
Planning Date
28-Jan-2021
Delivery Date
13-Jan-2022
Close Date
25-Feb-2022
Programme Priority
1
Overall Priority
Normal
Category
Compliance