Impact

Priority and Funding

This is a normal priority, core funded project.

 

Impact and Dependencies

Due to the heavy use of JIRA in different projects, the impact and dependencies of the upgrade need to be examined once downtimes are determined.

 

Lessons learned from previous projects

The lessons learned from last year and previous years upgrade projects have been reviewed and will be incorporated into this project.

 

Project Risks

Title Project Stage     Initial Risk    Current Risk    Management approach     Risk Owner
Application bugs Execute GREEN GREEN Avoid Alain Forrester
Development Technology Resources        Plan GREEN GREEN Reduce Mark Lang
Service Management Resources Plan GREEN GREEN Reduce Alain Forrester
Risk of low depth testing Execute GREEN GREEN Reduce Alain Forrester

Project Info

Project
Annual JIRA Upgrade
Code
COM061
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Bill Lee
Current Stage
Deliver
Status
In Progress
Start Date
06-Aug-2021
Planning Date
20-Aug-2021
Delivery Date
27-Oct-2021
Close Date
12-Nov-2021
Overall Priority
Normal

Documentation