Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for October 2021 October 2021 RED RED No Change
Report for September 2021 September 2021 RED RED No Change

Project Info

Project
Serengeti Bi-Annual Upgrade
Code
COM063
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Alex Carter
Current Stage
Plan
Status
In Progress
Start Date
10-Sep-2021
Planning Date
15-Dec-2021
Delivery Date
12-Mar-2022
Close Date
19-Mar-2022
Overall Priority
Normal