Report for September 2021

Report Date
September 2021

Project was due to start in Sep/Oct, but due to additional resource being provided to P&M, we do not have capacity within Project Services to start the project as planned. The delay in starting the project may impact Apps overall plan for 21/22 resulting in key projects not being delivered.

Project Status
RAG Status
Time
RED
Overall
RED
RAG Commentary
Project was due to start in September, but due to additional resource being provided to P&M, we do not have capacity within Project Services to start the project as planned. The delay in starting the project may impact Apps overall plan for 21/22 resulting in key projects not being delivered.
Change Status
Has formal escalation taken place?
Yes
Escalated to
Head of Project Services; Apps Director
Activity
Approved budget
200.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
200.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Annual Business Objects Upgrade
Code
COM064
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Alex Carter
Current Stage
Plan
Status
In Progress
Start Date
01-Nov-2021
Planning Date
26-Nov-2021
Delivery Date
22-Mar-2022
Close Date
15-Apr-2022
Overall Priority
Normal