API Upgrade - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
May 2022 BLUE 0.0 days 5.5 days 0.0
Content
Status
Withdrawn
Current Stage
Plan
Start Date
Monday, 14 March 2022
Planning Date
Friday, 8 April 2022
Delivery Date
Friday, 15 July 2022
Close Date
Friday, 29 July 2022
Project information
Project Code
COM068
Programme
ISG - Communication (COM)
Session
21/22
Organisational Unit
Application Development and Operations
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Funding Source
Core
Overall Priority
Normal